Complaint filed on behalf of private property farmland landowners in the San Luis Unit service area of the Central Valley Project in Central California

December 8, 2011

United States files Motion to Dismiss complaint based on statute of limitations

August 20, 2012

Hearing on United States’ Motion to Dismiss

September 30, 2013

Court issues Opinion and order denying United States’ Motion to Dismiss. The Court’s Opinion holds that the Bureau of Reclamation cannot “use decades of inaction, inconstancy and failures to deliver on its statutory duty and court-ordered responsibilities as an end-run around the statute of limitations regarding plaintiffs’ claim . . . . Fairness directs giving plaintiffs the opportunity to present evidence to the court on whether or not a taking has occurred based on defendant’s failure to provide a drainage solution for the Westlands for over fifty years.” (Revised final opinion filed on January 15, 2014)

October 25, 2013

Court stays case for six months pursuant to joint request by Parties based on ongoing settlement discussions between the Parties and other interested entities

May 15, 2014

Court extends stay of case for another six months pursuant to joint request by the Parties based on ongoing settlement discussions

November 18, 2014

Once again, the Court extends stay of case for another six months pursuant to joint request by the Parties based on ongoing settlement discussions